Blog Post Week 14

  • Status Report for Week 14
  • Tasks accomplished
    1. Completed User Testing
    2. Analyzed and reviewed test results
  • Tasks In Progress
    1. Create Final Presentation
    2. Update project package for final release
  • Tasks Planned For the Next Two Weeks
    1. Finish the above tasks
  • Issues
    1. Group coordination: Some of the team has not been invested in the project, missing deliverables and not being able to respond promptly to other group members.
  • Metrics

    1. Team
      1. Group meetings to talk about user testing and coordinate final delivery (1 hour)
      2. Analyze results (2 hours)
      3. Work on presentation (2 hours)
    2. Mike
      1. User Testing (2 hour)
    3. Richard
      1. User Testing (2 hour)
    4. Jeremy
      1. User Testing (2 hour)
      2. Interface work (2 hours)
    5. Bill
      1. Interface work (2 hours)
    6. Total: 47 hours